Progress Update 1st October 2007

The Bored Pile Foundation Work, was completed by PT Acset Indonusa in early September 2007.  This Contractor is now working on finalizing ‘shotcrete’ slope stabilization works which is approx. 70% complete.  

Excavation works are complete in the Mall and Office areas. Condominium excavation is underway by PT Jaya Teknik and expected to complete after Lebaran. This work includes backfilling of the basement perimeter retaining walls which will work closely in conjunction with the excavation. 

Substructure Work is executed by PT Total Bangun Persada. They have completed over 50% of Mall and Office basement slabs. A big mass concrete pour for the raft slab which totaled 10,700m3 in the Office area was successfully achieved at the end of September.

Curretly several tenders are being called for various Direct Contracts. These include Tenders for the main Superstructure Contract.




Welcome to Gandaria City Weblog

This weblog is intended to inform on a regular basis those interested in the progress of Gandaria City project. We try to keep it updated regularly but cannot guarantee it is current. We hope you will find it informative and useful. For more information please visit the Pakuwon.com link below.

 

October 2007
M T W T F S S
    Nov »
1234567
891011121314
15161718192021
22232425262728
293031  

Flickr Photos

Gandaria City Site Staff

More Photos

Categories

Blog Stats

  • 4,391 hits